List of questions which would help you to understand the pattern of questions on Project Time Management being asked in PMP Certification Exams.
(1) Milestones established by the customer must be adhered to by:
Answer:D
Hint: Both Project Manager and Functional Manager are responsible for project team and working towards achieving project milestones.
(2) The decision to request an increase the resources for a project is the responsibility of the:
Answer: B
Hint: It is Project Manager's responsibility.
(3) In which of the following project phases is the project schedule developed?
Answer: B
Hint: Refer Process and Knowledge area mapping on Page 61, PMBOK 5
(4) To crash a schedule you should:
Answer:D
Hint: See Crashing definition on Page 181, PMBOK 5
(5) The process of establishing the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule is known as
Answer:A
Hint: See Plan Schedule Management definition on Page 141, PMBOK 5
(6) Which of the following is NOT one of the primary needs for good project scheduling?
Answer: D
Hint: Effectiveness of trouble shooting procedures doesn't play a role in project scheduling
(7) The inputs used in the Define Activities process includes all but
Answer: D
Hint: See Figure 6-1, Page 143, PMBOK 5
(8) The successful project managers spend most of their time:
Answer: C
Hint: Communication takes nearly 90 percent of project manager's time.
(9) Resource leveling attempts to :
Answer: A
Hint: Read about Resource leveling on Page 179, PMBOK 5
(10) The tools and techniques used in Estimate Activity Durations exclude which of the following
Answer: D
Hint: See Figure 6-1, Page 143, PMBOK 5
(11) The Project Time Management Process consists of following seven processes:
a. Define Activities
b. Develop Schedule
c. Plan Schedule Activities
d. Sequence Activities
e. Estimate Activity Durations
f. Estimate Activity Resources
g. Control Schedule
The correct sequence is:
Answer: B
Hint: See Figure 6-1, Page 143, PMBOK 5
(12) The hierarchical representation of resources by category and type, which is useful for organizing and reporting project schedule data with resources utilization information is known as
Answer: C
Hint: Read about Resource Breakdown Structure on Page 165, PMBOK 5
(13) The representation of the plan for executing the project's activities including durations, dependencies, and other planning information, used to produce project schedules along with other scheduling artifacts is known as
Answer: B
Hint: See Schedule Model definition, Page 561, PMBOK 5
(14) A subsidiary plan that identifies a scheduling method and scheduling tool, and sets the format and establishes criteria for developing and controlling the project schedule is known as
Answer: A
Hint: See Schedule Management Plan definition, Page 561, PMBOK 5
(15) Which of the following is the output of the Plan Schedule Management process?
Answer: B
Hint: See Figure 6-1, Page 143, PMBOK 5
(16) The following inputs are used in both Sequence Activities and Estimate Activity Resources process, excluding
Answer: C
Hint: See Figure 6-1, Page 143, PMBOK 5
(17) What is the term for an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level
Answer: B
Hint: Refer to Rolling Wave planning on Page 152, PMBOK 5
(18) Abdullah, a project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which of the following process?
Answer: A
Hint: See Sequence Activities on Page 141, PMBOK 5
(19) The logical relationships under Precedence Diagramming Method (PDM) include:
Answer: D
Hint: See Precedence Diagramming Method on Page 156, PMBOK 5
(20) The method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS is known as:
Answer: B
Hint: Read about Bottom-up Estimating on Page 164, PMBOK 5
===================================================
- Activity Definition is typically performed by which of the following:
- Project Manager who created the WBS
- Project Team Members responsible for the work package
- Project Officer
- Project Stakeholder
- Which of the following is not an activity attribute:
- Person responsible for the activity
- Location where to perform the activity
- Time when to perform the activity
- Leads and Lags
- Which of the following does NOT generate changes to the Project documents:
- Define Activities
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Which of the following may generate a milestone list:
- Define Activities
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- In PDM, which of the following relationships is rarely used:
- Finish-to-Start
- Start-to-Finish
- Start-to-Start
- Finish-to-Finish
- A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
- Finish-to-Start
- Start-to-Finish
- Start-to-Start
- Finish-to-Finish
- A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
- ADM
- PDM
- A dependency with lag
- A dependency with lead
- The following BEST describes a subnetwork:
- Precedence Diagramming Method [PDM]
- Arrow Diagramming Method [ADM]
- Fragment Network
- Activity-On-Node [AON]
- A Project Manager in-charge of a Software Development projects is creating a project schedule network diagram for the code development component of the project. This is an example of:
- Precedence Diagramming Method [PDM]
- Arrow Diagramming Method [ADM]
- Fragment Network
- Activity-On-Node [AON]
- What-if scenario analysis is done as a part of which process:
- Sequence Activities
- Define Activities
- Develop Schedule
- Control Schedule
- AON refers to:
- Precedence Diagramming Method [PDM]
- Arrow Diagramming Method [ADM]
- Fragment Network
- Mandatory Dependencies
- AOA refers to:
- Precedence Diagramming Method [PDM]
- Arrow Diagramming Method [ADM]
- Fragment Network
- Mandatory Dependencies
- Activity Resource Requirements is an input to which of the following processes:
- Estimate Activity Durations
- Control Schedule
- Estimate Activity Resources
- Sequence Activities
- Dummy relationships or dummy activities can be used in which of the following Activity Sequencing techniques:
- Precedence Diagramming Method [PDM]
- Arrow Diagramming Method [ADM]
- Fragment Network
- Schedule Network Templates
- Which of the following is NOT an input to the Sequence Activities process:
- Project Scope Statement
- Activity Attributes
- Activity List
- Change Requests
- Which of the following is a technique for Sequence Activities:
- Precedence Diagramming Method [PDM]
- Arrow Diagramming Method [ADM]
- Rolling Wave Planning
- Mandatory Dependencies
- Reserve Analysis is a technique for:
- Define Schedule
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Resource Leveling is a technique for:
- Develop Schedule
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Following can be BEST described as a kind of dependency that can create arbitrary float values and limit scheduling options:
- Mandatory dependency
- Discretionary dependency
- Start-to-Finish dependency
- External dependency
- Critical path method is used in which of the following processes:
- Sequence Activities
- Define Activities
- Develop Schedule
- Estimate Activity Durations
- Parametric Estimating is done as a part of which process:
- Sequence Activities
- Develop Schedule
- Estimate Activity Resources
- Estimate Activity Durations
- Identification of Mandatory Dependencies is BEST done during which process:
- Sequence Activities
- Develop Schedule
- Define Activities
- Estimate Activity Duration
- Resource reallocation from non-critical to critical activities is an example of which Project Scheduling technique:
- Critical Path Method
- Schedule Compression
- What-if Analysis
- Resource Leveling
- Knowledge of best practices in a particular area is MOST likely to give rise to which of the following dependencies:
- Finish-to-Start dependency
- Soft Logic
- Mandatory dependency
- External dependency
- A Project Manager is preparing a Project Schedule network diagram. During the diagram development, she removes a dependency between two tasks that was defined in an earlier stage. After the network diagram is completed, she updates activity attributes for the two tasks. This is an example of:
- Define Activities
- Sequence Activities
- Develop Schedule
- Lack of change control
- Reserve Analysis involves:
- Estimating by multiplying the quantity of work by productivity rate
- Incorporating time buffers into the activity duration estimates
- Developing project schedule with contingency reserves as a recognition of the schedule risk
- Adding resource reserves to the activity resource estimates
- Which of the following is not true for Resource Leveling:
- Project schedule is build with resource buffers to prevent schedule slippage
- Project’s Critical path may be altered
- Resource based scheduling method
- Reverse resource allocation scheduling
Answers
- Answer: B PMBOK Pg. 134
- Answer: C Activity attributes are an input for project schedule development; therefore, the scheduling information is not a part of the activity attribute.
- Answer: A. Project document updates is an output to all processes in Project Time Management process area except Define Activities.
- Answer: A
- Answer: B
- Answer: A
- Answer: D Note that this dependency can be represented by both ADM and PDM techniques.
- Answer: C
- Answer: C It is not clear what Activity Sequencing technique is the Project Manager using; however, it is evident that she is developing a schedule network diagram for only part of the project (not the entire project)
- Answer: C
- Answer: A
- Answer: B
- Answer: A One of the outputs of Estimate activity resources is Activity Resource Requirements. Sequence Activities establishes logical dependencies between activities. Activity Resource requirements do not play an important role in determining the sequence.
- Answer: B
- Answer: D Approved Change Requests is not a valid input to Sequence Activities process.
- Answer: A
- Answer: D
- Answer: A
- Answer: B
- Answer: C
- Answer: D
- Answer: A
- Answer: D
- Answer: B Discretionary dependencies often result from best practices. This kind of dependency is also known as Soft Logic, Preferential Logic, or Preferred Logic.
- Answer: D The Project manager is preparing the project schedule network diagram which implies she is in the Activity scheduling process. This process can generate changes to the Activity definition and Activity Attributes; however, such changes should go thru the Integrated Change Control and only upon approval should they be made.
- Answer: B Answer C might seem more likely, but note the fine difference that Reserve Analysis is purely a technique of determining activity duration, not a schedule development technique.
- Answer: A Resource leveling involves